GATE 2026 · MN · NAT · 2 marks · Mineral Economics, Mine Planning, Systems Engineering › Linear Programming & Network Analysis

GATE 2026 Mining Engineering question: A mine workshop needs to assign 4 jobs to 4 service engineers. The cost for performing a…

A mine workshop needs to assign 4 jobs to 4 service engineers. The cost for performing a job by an individual service engineer is given. A typical job can be assigned to only one service engineer. If the service engineer S1 cannot perform the job J3, and S3 cannot perform the job J4, the optimal cost for completion of jobs is ______________. (answer in integer)

Service Engineer J1 J2 J3 J4
S1 50 50 --- 20
S2 70 40 20 70
S3 90 30 50 ---
S4 70 20 60 30
Show answer

Official answer: 130