GATE 2026 Mining Engineering question: The information for a dragline operation is given: Bucket capacity: 20 m 3 Bucket fill…
The information for a dragline operation is given:
Bucket capacity: 20 m
Bucket fill factor: 0.9
Digging and filling time: 20 s
Swinging (to and fro) time: 32 s
Dumping time: 10 s
Dragline utilization: 90%
The output of the dragline, in m h, is _________. (rounded off to one decimal place)
Show answer
Official answer: 938 to 942