The information for a dragline operation is given:

Bucket capacity: 20 m
Bucket fill factor: 0.9
Digging and filling time: 20 s
Swinging (to and fro) time: 32 s
Dumping time: 10 s
Dragline utilization: 90%

The output of the dragline, in m h, is _________. (rounded off to one decimal place)

Show answer

Official answer: 938 to 942