GATE 2026 · MN · NAT · 2 marks · Mining Methods and Machinery › Underground Coal Mining

GATE 2026 Mining Engineering question: A bord and pillar panel has 24 developed pillars of size 40 m × 40 m (centre to centre)…

A bord and pillar panel has 24 developed pillars of size 40 m × 40 m (centre to centre) under extraction. The following information is given:

Gallery width = 4 m
Extraction height = 3 m
Extraction ratio during depillaring = 80%
Specific gravity of coal = 1.4
Incubation period = 6 months
Average working days per month = 25

In order to extract the panel within the incubation period, the minimum rate of production, in tonne per day, is ______________. (rounded off to one decimal place)

Show answer

Official answer: 696 to 697