GATE 2026 Mining Engineering question: A bord and pillar panel has 24 developed pillars of size 40 m × 40 m (centre to centre)…
A bord and pillar panel has 24 developed pillars of size 40 m × 40 m (centre to centre) under extraction. The following information is given:
Gallery width = 4 m
Extraction height = 3 m
Extraction ratio during depillaring = 80%
Specific gravity of coal = 1.4
Incubation period = 6 months
Average working days per month = 25
In order to extract the panel within the incubation period, the minimum rate of production, in tonne per day, is ______________. (rounded off to one decimal place)
Show answer
Official answer: 696 to 697