GATE 2026 Petroleum Engineering question: Which of the following statements is/are CORRECT about the water injection well platforms?

Which of the following statements is/are CORRECT about the water injection well platforms?

  1. (A)

    These are meant for injection of gas through the injection well.

  2. (B)

    Metering devices are not required to determine injection rate of injection wells.

  3. (C)

    Metering devices are required to determine injection rate of injection wells.

  4. (D)

    Firefighting and life-saving equipment should be present on the platform.

Show answer

Official answer: C,D