GATE 2026 Production and Industrial Engineering question: The operation chart of a method of assembling nuts and bolts for a left-handed operator…

The operation chart of a method of assembling nuts and bolts for a left-handed operator has been illustrated in the figure.

Which ONE or MORE among the following options is/are CORRECT?

figure

  1. (A)

    The work distribution between the two hands is not balanced.

  2. (B)

    The two hands do not follow opposite motions.

  3. (C)

    The work is well distributed between the two hands.

  4. (D)

    The dominant hand of the operator performs majority of the tasks.

Show answer

Official answer: A,B