GATE 2026 · PI · MSQ · 2 marks · Industrial Engineering › Method Study & Work Measurement
GATE 2026 Production and Industrial Engineering question: The operation chart of a method of assembling nuts and bolts for a left-handed operator…
The operation chart of a method of assembling nuts and bolts for a left-handed operator has been illustrated in the figure.
Which ONE or MORE among the following options is/are CORRECT?

- (A)
The work distribution between the two hands is not balanced.
- (B)
The two hands do not follow opposite motions.
- (C)
The work is well distributed between the two hands.
- (D)
The dominant hand of the operator performs majority of the tasks.
Show answer
Official answer: A,B
Practise this question with exam-style marking