GATE 2026 Production and Industrial Engineering question: Consider an assembly line producing an item through a process involving three activities…

Consider an assembly line producing an item through a process involving three activities in the following order: cutting, welding, and polishing. There are three workers available: one is assigned only for cutting, one is assigned only for welding, and one is assigned only for polishing.

The activity time per item is given in the table.

Assuming that the process is running in steady state, the total number of items coming out of the assembly line in six hours is ______ (in integer).

Note: Assume that workers, items, and machines/tools are available as and when needed.

Activity name Cutting Welding Polishing
Activity time/item (in minutes) 30 40 25
Show answer

Official answer: 9