An underground copper mine sends 2500 tonnes of ore per day to the concentrator plant having an average grade of 1.2% Cu. The plant produces concentrate of 25.0% Cu with a recovery of 93.0%. The solids portion of tailings generated from the plant per day in tonnes is _____ (round off to 1 decimal place).

Show answer

Official answer: 2380 to 2396