GATE 2020 Production and Industrial Engineering question: A company has to perform five tasks (P, Q, R, S and T) to make an assembly. Task times…
A company has to perform five tasks (P, Q, R, S and T) to make an assembly. Task times and immediate predecessors of the tasks are listed below. If an assembly line is designed to obtain the maximum output rate, the efficiency of the line in % is ___________.
| Task | Task time (Seconds) | Immediate predecessor(s) |
|---|---|---|
| P | 20 | - |
| Q | 25 | P |
| R | 10 | Q |
| S | 15 | Q |
| T | 25 | R, S |
Show answer
Official answer: 95