GATE 2020 Production and Industrial Engineering question: In a work study experiment, it is observed that a worker completes a job in an average…
In a work study experiment, it is observed that a worker completes a job in an average time of 15 minutes with a performance rating of 120%. The time required for another worker having a performance rating of 80% to complete the same job (rounded off to one decimal place) in minutes is ___________.
Show answer
Official answer: 22.5