GATE 2021 set1 Civil Engineering question: A small project has 12 activities – N, P, Q, R, S, T, U, V, W, X, Y, and Z. The…
A small project has 12 activities – N, P, Q, R, S, T, U, V, W, X, Y, and Z. The relationship among these activities and the duration of these activities are given in the Table.
| Activity | Duration (in weeks) | Depends upon |
|---|---|---|
| N | 2 | - |
| P | 5 | N |
| Q | 3 | N |
| R | 4 | P |
| S | 5 | Q |
| T | 8 | R |
| U | 7 | R, S |
| V | 2 | U |
| W | 3 | U |
| X | 5 | T, V |
| Y | 1 | W |
| Z | 3 | X, Y |
The total float of the activity “V” (in weeks, in integer) is ______
Show answer
Official answer: 0