The soil profile at a construction site is shown in the figure (not to scale). Ground water table (GWT) is at 5 m below the ground level at present. An old well data shows that the ground water table was as low as 10 m below the ground level in the past. Take unit weight of water, kN/m.

figure

The overconsolidation ratio (OCR) (round off to two decimal places) at the mid-point of the clay layer is ______

Show answer

Official answer: 1.18 to 1.26