GATE 2021 · MN · MCQ · 2 marks · Mining Methods and Machinery › Underground Coal Mining

GATE 2021 Mining Engineering question: In a longwall panel, face is supported with shields of yield capacity 460 tonne per…

In a longwall panel, face is supported with shields of yield capacity 460 tonne per shield. The distance from the canopy tip to coal face is 0.15 m when the support is fully advanced. The depth of web is 0.60 m. The shields are set skin to skin at the face. Length of the canopy of the shield is 3.25 m and width 1.5 m. Setting capacity is 80% of the yield capacity. The setting resistance at the maximum and minimum span of the coal face, in tonne/m, respectively are

  1. (A)

    61.33 and 72.15.

  2. (B)

    63.72 and 75.48.

  3. (C)

    76.66 and 90.19.

  4. (D)

    91.99 and 108.22.

Show answer

Official answer: A