A cement company has three factories which transport cement to four distribution centres. The daily production of each factory, the demand at each distribution centre, and the associated transportation cost per tonne from factory to distribution centre are given in the Table.

Distribution centre

D D D D Supply (tonnes/day)
Factory F 20 30 110 70 600
F 10 0 60 10 100
F 50 80 150 90 1000
Demand (tonnes/day) 700 500 300 200

The initial basic feasible solution using the least-cost rule is _____. [in integer]

Show answer

Official answer: 112000