GATE 2022 · MN · NAT · 2 marks · Mining Geology, Mine Development and Surveying › Explosives & Blast Design

GATE 2022 Mining Engineering question: Following information is given for a drilling operation to be carried out for overburden…

Following information is given for a drilling operation to be carried out for overburden removal in a surface mine.

Volume of rock blasted per round, m : 3,20,000
Number of blast holes : 100
Drill hole diameter (D), mm : 200
Length of subgrade drilling : 8D
Stemming length : 25D
Bench height, m : 30
Powder factor, m/kg : 3.2

The amount of explosive per unit length of charge in kg/m, is_______. (round off to two decimal places)

Show answer

Official answer: 36 to 39