GATE 2022 Mining Engineering question: The shaft-top coordinates of two vertical shafts are given below. The depth of the shaft…

The shaft-top coordinates of two vertical shafts are given below. The depth of the shaft A and B are 200 m and 149 m, respectively.

Shaft Latitude (m) Departure (m) Surface RL (m)
A N670.0 W150.0 250
B N170.0 E50.0 209

The downward gradient of the line joining the bottom of the two shafts in degrees, is_______. (round off to two decimal places)

Show answer

Official answer: 0.9 to 1.13