GATE 2022 Mining Engineering question: A mine has a reserve of 150 million tonne (Mt) and is designed for a maximum production…
A mine has a reserve of 150 million tonne (Mt) and is designed for a maximum production capacity of 5 Mt per year. In the first year the production is 2 Mt and it increases by 20% each year. The reserve in Mt that remains at the end of 15 years, is_______. (round off to two decimal places)
Show answer
Official answer: 84.8 to 85.5