GATE Assistant

Past questions › Mining Engineering › GATE 2022

GATE 2022 · MN · NAT · 2 marks · Mineral Economics, Mine Planning, Systems Engineering › Linear Programming & Network Analysis

GATE 2022 Mining Engineering question: Information on Activity-Time duration of a project is provided below Activity…

Information on Activity-Time duration of a project is provided below

Activity Predecessor event Successor event Pessimistic Most likely Optimistic
A 1 2 20 15 4
B 1 3 12 8 4
C 2 3 16 11 6
D 3 4 20 13 12
E 2 4 13 8 3
F 1 4 45 35 25

(Estimated Time Duration (weeks): Pessimistic, Most likely, Optimistic)

The expected project duration in weeks, is_______. (in integer)

Show answer

Official answer: 39

Practise this question with exam-style marking

Discussion

No discussion yet.

Join the discussion