GATE 2022 Mining Engineering question: Information on Activity-Time duration of a project is provided below Activity…
Information on Activity-Time duration of a project is provided below
| Activity | Predecessor event | Successor event | Pessimistic | Most likely | Optimistic |
|---|---|---|---|---|---|
| A | 1 | 2 | 20 | 15 | 4 |
| B | 1 | 3 | 12 | 8 | 4 |
| C | 2 | 3 | 16 | 11 | 6 |
| D | 3 | 4 | 20 | 13 | 12 |
| E | 2 | 4 | 13 | 8 | 3 |
| F | 1 | 4 | 45 | 35 | 25 |
(Estimated Time Duration (weeks): Pessimistic, Most likely, Optimistic)
The expected project duration in weeks, is_______. (in integer)
Show answer
Official answer: 39