GATE Assistant

Past questions › Production and Industrial Engineering › GATE 2022

GATE 2022 · PI · NAT · 2 marks · Operations research and Operations management › Engineering Economy & Costing

GATE 2022 Production and Industrial Engineering question: A company is planning to produce 24 electric cars per day. The setup cost of the plant…

A company is planning to produce 24 electric cars per day. The setup cost of the plant is estimated as ₹ 19476 million and the variable cost is ₹ 0.6 million per car. The car will be sold at a price of ₹ 1.5 million. The number of days required for achieving the breakeven is______________. [round off to nearest integer]

Show answer

Official answer: 900 to 905

Practise this question with exam-style marking

Discussion

No discussion yet.

Join the discussion