A company forecasts the weekly demand of oxygen cylinders using exponential smoothing method with smoothing constant . The actual demands in Week 1, Week 2, Week 3 and Week 4 were 375, 412, 592 and 439 units, respectively. The forecasted demand for Week 3 was 500 units. The forecast (in unit) for the Week 5 is______________. [in integer]

Show answer

Official answer: 500 to 505