GATE 2023 Mining Engineering question: Data related to a surface miner operation are given below - Drum width (m) = 3.0 Average…
Data related to a surface miner operation are given below -
Drum width (m) = 3.0
Average cutting depth (cm) = 20
Average cutting speed (m/min) = 25
Length of pit (m) = 500
Turning time (min) = 2
Truck exchange time (s) = 30
Truck capacity (m) = 15
Considering in situ volume, the production rate of the surface miner in m/hr, is _____.
[rounded off to 1 decimal place]
Show answer
Official answer: 555 to 578