GATE 2023 · MN · NAT · 2 marks · Mining Methods and Machinery › Underground Coal Mining

GATE 2023 Mining Engineering question: A continuous miner served by two shuttle cars produces 240 tonne/hr. The capacity of…

A continuous miner served by two shuttle cars produces 240 tonne/hr. The capacity of each shuttle car is 10 tonne. When a single shuttle car operates, the cycle time becomes 4 min. In case one of the shuttle cars is under break-down, the reduction in hourly production from that of two cars in percent is _____.

[rounded off to 1 decimal place]

Show answer

Official answer: 37 to 38