Consider the statements P and Q.

P: Client’s Preliminary Estimate is used for budgeting costs toward the end of planning and design phase.

Q: Client’s Detailed Estimate is used for controlling costs during the execution of the project.

Which one of the following options is CORRECT?

  1. (A)

    Both P and Q are TRUE

  2. (B)

    P is TRUE and Q is FALSE

  3. (C)

    Both P and Q are FALSE

  4. (D)

    P is FALSE and Q is TRUE

Show answer

Official answer: A