GATE 2024 set1 Civil Engineering question: Consider the statements P and Q. P: Client’s Preliminary Estimate is used for budgeting…
Consider the statements P and Q.
P: Client’s Preliminary Estimate is used for budgeting costs toward the end of planning and design phase.
Q: Client’s Detailed Estimate is used for controlling costs during the execution of the project.
Which one of the following options is CORRECT?
Show answer
Official answer: A