GATE 2024 set1 · CE · MCQ · 1 mark · Structural Engineering › Construction Materials & Management

GATE 2024 set1 Civil Engineering question: The following figure shows the arrangement of formwork for casting a cantilever RC beam.…

The following figure shows the arrangement of formwork for casting a cantilever RC beam.

figure

The correct sequence of removing the Shores/Props is

  1. (A)

    S1→S2→S3→S4→S5

  2. (B)

    S5→S4→S3→S2→S1

  3. (C)

    S3→S2→S4→S1→S5

  4. (D)

    S3→S4→S2→S5→S1

Show answer

Official answer: B