GATE 2024 · MN · MCQ · 2 marks · Mineral Economics, Mine Planning, Systems Engineering › Linear Programming & Network Analysis

GATE 2024 Mining Engineering question: Data from two production faces of an open pit iron ore mine are given. Item description…

Data from two production faces of an open pit iron ore mine are given.

Item description Face 1 Face 2
Maximum production capacity (tonne/day) 1600 2000
Fe (%) 63 58
Production cost of ores (in INR/tonne) 1500 1200

Ores from two different faces are blended and supplied with Fe grade not less than 60 %. Based on the demand, the combined production is limited to a maximum of 2500 tonne/day. If the selling price of blended iron ores is INR 4500 /tonne, the optimal production from two faces in tonne/day, for maximizing the profit, respectively are

  1. (A)

    1000.0 and 1500.0

  2. (B)

    1333.3 and 1166.7

  3. (C)

    1600.0 and 900.0

  4. (D)

    500.0 and 2000.0

Show answer

Official answer: A