GATE Assistant

Past questions › Production and Industrial Engineering › GATE 2024

GATE 2024 · PI · MCQ · 2 marks · Operations research and Operations management › Project Management: CPM & PERT

GATE 2024 Production and Industrial Engineering question: A project has six activities and the precedence relationship among them is shown in the…

A project has six activities and the precedence relationship among them is shown in the table.

Activity Precedent activities
A None
B None
C None
D A, B
E B, C
F A, B

The minimum number of dummy activities needed to draw an activity-on-arrow (AOA) representation of the project network is

  1. (A)

    0

  2. (B)

    1

  3. (C)

    2

  4. (D)

    3

Show answer

Official answer: D

Practise this question with exam-style marking

Discussion

No discussion yet.

Join the discussion