GATE 2024 Production and Industrial Engineering question: A project has six activities and the precedence relationship among them is shown in the…
A project has six activities and the precedence relationship among them is shown in the table.
| Activity | Precedent activities |
|---|---|
| A | None |
| B | None |
| C | None |
| D | A, B |
| E | B, C |
| F | A, B |
The minimum number of dummy activities needed to draw an activity-on-arrow (AOA) representation of the project network is
Show answer
Official answer: D