GATE Assistant

Past questions › Production and Industrial Engineering › GATE 2024

GATE 2024 · PI · MCQ · 2 marks · Operations research and Operations management › Linear Programming & Duality

GATE 2024 Production and Industrial Engineering question: Consider the following linear programming problem with two decision variables x 1 and x…

Consider the following linear programming problem with two decision variables and . There are three constraints involving resources R1, R2 and R3 as indicated.

Maximize

Subject to

R1

R2

R3

,

The optimal solution of the problem is: and .

For which one of the following options, the shadow price of the resource(s) will have non-zero value(s)?

  1. (A)

    R1, R2 and R3

  2. (B)

    R1 and R2

  3. (C)

    R2 and R3

  4. (D)

    R1 only

Show answer

Official answer: C

Practise this question with exam-style marking

Discussion

No discussion yet.

Join the discussion