GATE 2025 Mining Engineering question: In a shovel dumper combination, the loading time of a dumper is 3 minutes. The shovel…
In a shovel dumper combination, the loading time of a dumper is 3 minutes. The shovel serves 8 dumpers. If the cycle time of a dumper including its loading time is 22 minutes, the waiting time of a dumper, in minute, is____ (in integer)
Show answer
Official answer: 2