GATE 2025 Mining Engineering question: An HMX explosive having Velocity of Detonation (VOD) of 10500 m/s is tested by…

An HMX explosive having Velocity of Detonation (VOD) of 10500 m/s is tested by D’Autriche method with a detonating fuse of VOD 7000 m/s, as shown in the figure. The impression mark on lead plate will be obtained at a distance (L), in m, from the midpoint of the fuse, is ___ (rounded off to two decimal places)

figure

Show answer

Official answer: 0.3 to 0.35