GATE 2026 set1 Civil Engineering question: The maximum demand at a water purification plant has been estimated as 12 million litres…

The maximum demand at a water purification plant has been estimated as 12 million litres per day. For the raw supplies, a rectangular sedimentation tank is to be designed with mechanical sludge removal arrangement. Consider depth of the tank as 4 m, detention period as 6 hours, and velocity of flow as 0.003 m/s.

The width (in m) of the detention tank is _________ (rounded off to two decimal places).

Show answer

Official answer: 11 to 12