GATE 2026 Mining Engineering question: Dust particles from a blasting operation rise up in the atmosphere to a height of 500 m.…

Dust particles from a blasting operation rise up in the atmosphere to a height of 500 m. The viscosity of air is kg m s. Assume the particles have quiescent settling (no turbulence) in atmosphere. Neglecting air density, the settling time, in days, of a dust particle of 2.5 µm diameter and 3600 kg m density is ______________. (rounded off to two decimal places)

Show answer

Official answer: 8 to 10