Which ONE of the following is NOT an assumption of the economic order quantity (EOQ) model?

  1. (A)

    Demand is known and deterministic.

  2. (B)

    Lead time is zero.

  3. (C)

    Stockouts are permissible.

  4. (D)

    Holding cost for the quantity in stock is linearly increasing with the order quantity.

Show answer

Official answer: C