GATE 2026 Production and Industrial Engineering question: Painting is one of the activities in a construction project. For the painting activity…

Painting is one of the activities in a construction project. For the painting activity that takes 6 days, both the total float and the free float are zero.

Which ONE of the following is TRUE for the painting activity?

  1. (A)

    Painting is a dummy activity.

  2. (B)

    Painting is a non-critical activity.

  3. (C)

    The start of painting activity can be delayed without causing delay in completion of the construction project.

  4. (D)

    The start of painting activity cannot be delayed without causing delay in completion of the construction project.

Show answer

Official answer: D